文档介绍:目录
工程概况--------------------------------------------2
编制依据--------------------------------------------2
施工部署--------------------------------------------2
-------------------------------------------2
---------------------------------------3
施工准备工作----------------------------------------4
-----------------------------------------------4
钢支撑制作------------------------------------------4
-------------------------------------4
-----------------------------------------------4
-----------------------------------------------5
------------------------------------- 5
------------------------------ 6
---------------------------------- 7
钢支撑安装----------------------------------------- 8
------------------------------------- -8
---------------------------------- 9
------------------------------------------ 9
质量保证措施及质量保证体系-------------------------11
施工安全措施---------------------------------------12
安全生产及文明施工保证措施-------------------------13
----------------------------13
----------------------------------13
------------------------------15
----------------------------------15
—----------------------------------------15
一、工程概况
厂房,主要为单层钢结构和砼主体二层厂房。单层钢结构厂房面积为4548m2,~12米,而吊顶完成面为4米,~8左右,,故本工程设置角钢50*5钢结构反向支撑。
二、编制依据
依据现有吊顶钢结构反向支撑设计图纸:
1.《钢结构工程施工质量验收规范》(GB50205-2001)
3.《建筑钢结构焊接规程》(JGJ81-2002)
5.《工程测量规范》(GB50026-93)
6.《涂装前钢材表面锈蚀等级和防锈等级》(GB8923-88)
7.《钢结构高强螺栓连接的设计、施工及验收规范》(JGJ82-91)
三、施工部署
经理
行政副经理
总工程师
生产副经理
技术科
质检科
财务科
劳资科
食
堂
材料科
生产科
安全科
下料车间
安装小组
油漆车间
焊接车间
装配车间
钢结构制作安装劳动力需用计划:
序号
项目
电焊工
钳工
油漆工
信号工
杂工
合计
1
厂内
制作
4
2
4
2
10
2
现场
安装
6
1
1
1
6
15
合计
10
3
5
1
8
25
劳动力分布情况:
工序
电焊工
钳工
油漆工
其他
合计
下料及型钢矫正
2
1
1
4
型钢打孔、油漆
1
2
4
2
9
现场
安装
6
1
1
5
13
合计
9