文档介绍:编制说明及编制依据---------------------------------------------------------------------------1
工程概况------------------------------------------------------------------------------------------1
确定用电布置------------------------------------------------------------------------------------1
负荷计算------------------------------------------------------------------------------------------2
变压器的选择------------------------------------------------------------------------------------3
各电箱内电器的选择---------------------------------------------------------------------------6
接地、防雷装置的设计------------------------------------------------------------------------14
系统接线图--------------------------------------------------------------------------------------16
电气设备平面图---------------------------------------------------------------------------------17
防护措施------------------------------------------------------------------------------------------17
安全用电技术措施------------------------------------------------------------------------------18
用电防火措施------------------------------------------------------------------------------------20
安全技术管理------------------------------------------------------------------------------------22
14、应急预案-----------------------------------------------------------------------------------------24
1 编制说明及编制依据
编制说明
本临时用电组织设计中,凡未注明计量单位的均为“mm”。
本临时用电组织设计中,加黑体字部分为标准强制性条文。
本临时用电组织设计为公司所属分公司、项目部编制临时用电组织设计的范例,各单位应按工程的实际情况编制。
编制依据
本工程施工图(包括图纸会审记录、设计变更等设计文件);
本工程施工组织设计;
《施工现场临时用电安全技术规范》(JGJ46-2005);
《建筑施工安全检查标准》(JGJ59-99);
《建设工程施工现场供用电安全规范》GB50194-93;
《建筑机械使用安全技术规程》(JGJ33-2001);
南宁市用电安全规范;
公司机电管理制度、标准:
1、公司质量、环境和职业健康安全管理体系程序文件、作业文件;
2、公司《现场临时用电安装、使用、维护和拆除施工工艺标准》。
2 工程概况
工程名称:星湖小区住宅配套综合楼
地点:南宁市民族大道与星湖二里交汇处
工程建筑面积18640m2,层数为地下一层,地上十三层,。工期为500天。
工地附近的高压(10KV)架空线路与建筑物外墙面的距离符合要求,不需要进行外电防护。
施工现场无地下管线和沟道,不需进行防护。
工地西侧距本工程约30米处,有建设单位提供的临时用电线路能满足使用要求,施工用电拟从此引出。
3 确定用电布置
机械设备选用、布置。