摘要:详细介绍了昆明掌鸠河引水供水工程厂口隧洞检修支洞主洞穿越坍方区及断层带的施工方案,内容包括坍方冒顶情
况描述、地表陷穴处理、洞内坍方体处理和穿越坍方区施工步骤与技术措施。施工实践表明,所介绍的施工方案合理可行,
效果良好。
关键词:隧道;坍方;施工方案
中图分类号:U 文献标识码:A
Construction scheme of tunnel passing through
landslide area and fault zone
WANG Ke-li
( School of Civil Engineering, Shijiazhuang Railway Institute, Shijiazhuang 050043, China )
Abstract: The construction scheme of tunnels passing through landslide area and fault zone of the repair tunnel for Changkou water
tunnel of Zhangjiu River water diversion and supply project in Kunming is introduced in detail, including such contents as description
of tunnel collapse to ground surface, ground settlement pit treatment, collapse body treatment in tunnel, constructuon procedure and
technical measures of pass through landslide area. Construction practice has shown that the tunnel collapse treatment scheme is
reasonable, reliable and effectual.
Key words: tunnel; landslide; construction scheme
1 引言 2 坍方冒顶情况
昆明掌鸠河引水供水工程“输水工程土建Ⅵ厂口隧洞检修支洞主洞上游于 2002 年 11 月 25
标”的主要工程是厂口隧洞,该隧洞全长 11 日掘进到 D79+803 处时,上导掌子面发生小规模坍
m(D74+~D85+),地质条件十分复塌现象,为防止出现坍方冒顶事故,当时决定采取
杂,尤其是厂口隧洞检修支洞主洞 D79+~ 堆码砂袋封闭掌子面注浆加固措施。掌子