文档介绍:浅谈坝基砂砾石层水泥砂浆充填注浆施工工艺与应用
付建国冯海艳
中国水利水电第六工程局有限公司辽宁 118003
【摘要】杨东河水电站面板堆石坝基础为砂卵砾石层,砂卵砾石地层基础具有结构松散、孔隙率大、渗透性强等特点。水泥砂浆充填注浆能有效提高坝基承载能力、增强坝基砂卵砾石层的密实度、从而增强大坝基础的防渗能力。本文主要介绍坝基砂砾石层水泥砂浆充填注浆施工中所采用的施工方案、施工工艺及相关经验,为今后类似工程施工提供参考经验。
【关键词】坝基砂卵砾石层充填注浆工艺与应用
Abstract Yang River concrete face rockfill dam base is the basis of the gravel layer, sand and gravel stratum has a loose structure, porosity, permeability, and other characteristics. Fill grouting cement mortar can effectively improve the dam foundation bearing capacity, enhance the density of the dam foundation gravel layer, thereby enhancing the ability of the dam foundation seepage control. This paper describes the construction program in the dam foundation of sand and gravel layer of cement mortar fill grouting construction, construction technology and experience, provide a reference for future similar construction experience.
Keywords: colluvial slope; landslide; geological evaluation; formation mechanism...
中图分类号: 文献标识码:A 文章编号:
1、工程概况
杨东河坝枢工程河床段坝基砂砾石层水泥砂浆充填注浆施工,处于大坝砼防渗墙下游河床段45m范围,根据设计要求对该范围内的砂砾石层进行水泥砂浆注浆处理,以改善坝基承载力条件。注浆孔垂直于坝轴线方向从A~S排共19排,平行坝轴线方向有A排41个孔,B排40个孔,依此循环,,孔距为3m,排间布孔呈梅型布置,共计770个孔,分七个单元进行施工,总注浆段长约为6500m。其中包含18个先导孔,上游A排、中间J排、下游S排每排各6个,每排的先导孔间距24m。
砼防渗墙下游河床段45m范围坝基覆盖层地质情况分两种,左右靠近岸坡附近为第四系崩坡积土积块石、巨石层,最大粒径可达10m左右,局部有架空,泥质含量较多、土质稍密。中部河床段为冲洪积砂卵砾石层,厚度在12~17米,底部存在孤石;颗粒级配较差,砂卵砾石层粒径>%、粒径