文档介绍:伟岸城二期工程
(98#楼~105#楼)
土
方
开
挖
施
工
方
案
二0一三年九月
目录
编制依据·······································1
工程概况·······································1
施工部署·······································2
土方开挖方案···································2
质量技术组织措施·······························5
主要管理措施···································7
雨季施工·······································10
应急预案·······································12
基坑监测方案···
································13
基坑安全保证措施·······························15
附图·········································15
一、编制依据
该施工方案编制的主要依据:招投标文件、设计图纸、本工程施工组织设计;建设部现行规范、规程及成都市有关规程。主要规范、规程如下:
建质《2003(82号)》建筑工程预防坍塌事故若干规定
《建筑边坡工程技术规范》GB50330-2002
《建筑与市政降水工程技术规范》(JGJ/T111-98)
《建筑地基基础工程施工质量验收规范》(GB50202-2002)
《建筑施工安全检查标准》(JGJ59-99)
《建筑施工手册》(第四版)2003 年
《建筑工程施工质量验收统一标准》GB50