文档介绍:目录一、编制依据及工程概况........................................................................................................................................................................................2二、施工措施................................................................31、施工测量前准备.............................................................32、沟槽开挖...................................................................43、管道基础...................................................................54、管道铺设...................................................................55、管道接口...................................................................56、闭水试验...................................................................67、沟槽回填...................................................................68、检查井施工:...............................................................69、沟槽支护结构设计...........................................................7三、施工进度计划...............................................................................................................................................................................................13四、质量保证体系及措施................................................................................................................14五、安全保证体系及措施.....................................................15六、文明施工保证措施.......................................................16七、环境保护及防止施工扰民措施.............................................17八、雨季施工施工措施.......................................................19一、;建设单位提供的相关资料;国家、行业及验收规范、工程质量检验评定标准及相关法规等;公司《质量、环境和职业健康安全管理手册》和程序文件;本工程的现场条件、施工特点及类似工程的施工经验;我公司现有资源和其它可利用资源;(规划16号路)工程位于西起兴凯路,向东延伸至已建奉钱路,,,道路红线宽度为24m,共有1#桥、2#桥2座桥梁。主要工程内容为道路工程、桥梁工程、管线工程、交通工程、景观绿化工程、道路配套设施工程等施工。工程工期为300天,。质量达到国家施工验收规范一次性验收合格标准;安全达到合格标准。(一)、雨水管道本工程雨水管道布置于道路北侧车道下,距离道路中心线5米位置处。雨水管道分段排入榭北排洪干河内,雨水主管管径雨水管道管径DN600mm~DN1350,m雨m水支管管径为DN300m。m雨水管道采用国标钢