文档介绍:目 录1编制说明.............................................................................................................12工程概况.............................................................................................................13编制依据.............................................................................................................14施工应具备的条件及施工准备.........................................................................15机泵设备的安装.................................................................................................36灌浆.....................................................................................................................47机械安装的具体技术要求.................................................................................48设备拆检及装配措施.........................................................................................69质量保证措施.....................................................................................................610环境、职业、安全、健康...............................................................................711劳动力组织.......................................................................................................712工序质量控制...................................................................................................713主要施工机具...................................................................................................814施工进度控制表...............................................................................................8乌海***碱工程 VCM装置机泵类设备安装施工方案编制说明本方案仅适用于乌海***碱工程***乙烯装置机泵类设备安装试车。工程概况乌海***碱工程***乙烯装置中,共有机泵类设备63台,其中国产泵53台,进口泵10台(详见附表1)。《化工机器安装工程施工及验收规范(通用规定)》HGJ203-《化工机器安装工程施工及验收规范(化工用泵)》HGJ207-《化学工业工程建设交工技术文件规定》G2023T-《压缩机、风机、泵安装工程施工及验收规定》GB50275-《机械设备安装工程施工验收通用规范》GB50231-《石油化工施工安全技术规程》SH3505-、资料(包括出厂合格证明书、安装及使用说明书、装箱单)规范齐全。、材料到位,现场具备“三通一平”的施工条件。、说明书、工号技术负责人应对施工人员进行技术交底。、结构型式等定出垫铁规格及用量,准备好垫铁。 (垫铁的规格、尺寸见附表 3)***碱工程 VCM装