文档介绍:吸收塔施工方案1倒装法目录··································································1··································································1························································3··························································6··········································16··················································18······································22······································································24工程概况虎山电厂烟气脱硫工程脱硫装置采用石灰石——石膏湿法工艺,副产物为二水石膏。本工程脱硫装置设置为两套,#1脱硫装置单独处理#1炉烟气,#2脱硫装置单独处理#2炉烟气,,每塔设置两层除雾层、四层喷淋层,设计条件下,全烟气脱硫效率为≥%。施工范围、接口界限#1吸收塔布置在烟囱南方向,#2吸收塔布置在烟囱北方向,#1、#2吸收塔以烟囱为中心相互对称布置。吸收塔基础为钢筋混凝土基座。吸收塔直径为φ16200mm,为全钢制圆筒薄壁容器。上段筒体为除雾喷淋区,下部筒体为浆液循环搅拌回收系统。,塔体重约650吨(不含外平台楼梯栏杆、内部管道设备件)。吸收塔安装施工范围为:地脚螺栓、底板隔栅、底板、下部筒体、上部筒体、内部浆液循环回收搅拌系统、平台楼梯栏杆、设备、内部烟气除雾和喷淋系统及设备的制作与安装等。吸收塔安装烟气接口界限为吸收塔中部的原烟气入口至吸收塔顶部的净烟气出口,吸收塔的扰动、氧化、除雾、喷淋以及浆液循环管道、浆液排出管道的接口界限为吸收塔筒体壁板上的管桩口法兰以内。主要工程量、特征参数吸收塔底部设备(基础底板、埋件和地脚螺栓):约20吨(两台量);吸收塔筒体及加强环:约650吨(两台量);吸收塔平台楼梯栏杆:65吨;2级除雾器设备及其系统:一套(一台量);Φ400扰动设备及其系统:一套(一台量);4层喷淋装置及其系统:一套(一台量);氧化设备及其系统:一套(一台量);内部浆液循环回收搅拌设备及系统:一套(一台量)。施工重点、难点该吸收塔安装工程施工重点难点在于地脚螺栓、基础环板的安装和底板安装的平整度控制;焊接变形的控制。编制依据序号名称标准号1工程建设标准强制性条文(电力工程部分)(2006年版)2烟气脱硫工程施工质量验收及评定规程DL/T5417-20093烟气脱硫吸收塔施工及验收规程DL/T5418--20025基本建设工程启动及竣工验收规程(1996版)6钢结构工程施工质量验收规范GB50205—20017焊工技术考核规程DL/T679-19998焊接工艺评定规程DL/T868-20049钢结构焊接技术规程DL/T678-199910压力容器无损检测JB/T4730-200511钢制压力容器GB150-199812钢制压力容器焊接工艺评定JB4708-200013钢制压力容器焊接规程JB/T4709-200014钢制压力容器产品焊接试板的力学性能试验JB4744-200015超声探伤用探头性能测试方法JB/T10062-199916钢焊缝手工超声波探伤方法和探伤结果分级GB11345-8917钢管环缝熔化焊焊接接头射线透明工艺和质量分级GB/T12605-9018异种钢焊接技术规程DL/T752-200119电力工业无损检测人员资格考核规则DL/T675-~5-8421电站钢结构焊接通用技术条件DL/T678-199922紧固件螺栓、螺钉、螺柱和螺母通用技术条件GB/T16938-199723铸造三通、弯头超声波探伤方法DL/T718-200024钢管焊接接头超声波检验你技术规程DL/T820-200225钢制承压管道对接焊接接头射线检验技术规范DL/T821-200226立式圆筒形钢制焊接油罐施工及验收规范GB128-9027钢制焊接常压容器JB/T4735—199728机械设备安装工程施工及验收规范TJ23129热力设备和管道保温材料技术条件及检验方法SDJ68-8530钢结构高强度螺栓连接的设计、施工及验收规程JGJ82--2012