文档介绍:污水处理深基坑土方工程(26000m3/d)施工组织设计目录-I-目录第一章基坑特点..........................................................................................................1第二章基坑土方开挖施工..........................................................................................1第一节施工前准备..................................................................................................1第二节基坑开挖顺序..............................................................................................2第三节车辆行车及机械配备..................................................................................3第四节施工降水与排水措施..................................................................................3第三章组织与协调管理及工期..................................................................................4第四章基坑支护措施..................................................................................................4第一节基坑围护设计方案与分析..........................................................................4第二节围护设计......................................................................................................5第三节围护施工......................................................................................................5第五章应急措施及注意事项......................................................................................6第一节预防措施......................................................................................................6第二节应急措施......................................................................................................6第三节注意事项......................................................................................................6第六章基坑四周的安全围护......................................................................................6第七章土方回填..........................................................................................................7第八章安全文明施工..................................................................................................8第一节安全施工措施............................................................................