文档介绍:浅谈220kV电缆较长距离试验方法
ABSTRACT:In recent years, with the rapid development of urban power grid construction, high voltage cable has been widely used, this bined with 220kV East Green Change - traction cable line project, the cable from the long, cross-section of more interconnected, according to the cable transfer of test specification, the actual situation of the construction site, a detailed description of the 220kV cable pilot projects over test timing, the choice of test equipment and test methods development; test security measures.
KEY WORDS: Over test of 220kV cables;test time ;test equipment; test methods ; safety measures
摘要:近年来,随着城市电网建设的飞速发展,超高电压等级的电缆也被广泛使用,本文主要结合220kV东青变-牵引变电缆线路工程,电缆距离较长,交叉互联段较多,根据电缆交接试验规范规定、施工现场的实际情况,详细的介绍了220kV电缆交接试验的试验项目时间的安排、试验仪器设备的选择及试验方法的制定;试验的安全措施。
关键字:220kV电缆交接试验试验时间试验仪器设备试验方法安全措施
0引言
220kV东青~常州牵引站工程为沪宁城际高铁重要配套供电项目,线路分别始于220kV东青变电站北起#1构架、#16构架,止于常州牵引站东起#1构架、#2构架。,电缆型号为ZR-YJLW03-127/220-1*1600。YJLW03 1×1600mm2,电缆敷设方式为电缆沟、箱涵、桥架、顶管通道敷设,由于工期短,任务重,电缆敷设、接头施工完毕后,送点节点只剩7天时间,电缆试验合格与否直接关系到验收送电时间,所以合理安排试验时间,选择便于操作、满足试验要求的试验仪器及设备,制定详细的试验方案,尤为关键。根据交接试验规范,220kV电缆试验项目如下:
;
;
;
;
;
;
;
;
;
;。
。
。
:
试验项目
计划试验时间
计划试验地点
2010年3月16日
220kV牵引变电所
2010年3月16日
220kV东青变电所
2010年3月16日
220kV牵引变电所
2010年3月16日
中间接头井
2010年3月16日
中间接头井
2010年3月17日
220kV东青变电所
2010年3月18日
220kV牵引变电所
由于电缆线路长,又是双回路,交叉互联段多,故试验项目繁多,通过对上述试验项目时间的合理安排,总的计划交接试验时间为3天,能为竣工送电争取时间。是否能在合理时间内完成试验项目,那么试验仪器设备的选择就十分重要。
2试验仪器及设备的选择
试验项目
通用工程试验设备
本工程选择试验设备
核相仪
高压兆欧表5000V
高压兆欧表10 kV
高压兆欧表10 kV
双臂电桥
直流电阻测试仪
直流高压发生器
高压兆欧表10kV
1000V兆欧表
1000V兆欧表
双臂电桥