文档介绍:MSS 移动模架逐孔施工连续梁桥预拱度设置方法
岳力强,刘钊
(东南大学土木工程学院,江苏南京 210096)
摘要:通过对移动模架逐孔施工连续梁桥线形特点的分析,根据预拱度设置的原理和方法,
结合移动模架法的施工特点,归纳总结了移动模架施工连续梁预拱度设置的方法,并在苏通
大桥引桥施工过程中应用。此方法对于同类桥梁预拱度设置具有一定的借鉴作用。
关键词:移动模架、预应力混凝土、连续箱梁、线形控制、预拱度设置
Pre-camber setting method during the span-by-span construction of
continuous girder bridge with MSS
Yue Liqiang, Liu Zhao
(College of Civil Engineering, Southeast University, Nanjing 210096, China)
Abstract: This paper analyzes the deflection character of bridge construction with MSS, and
summarizes the Pre-camber setting method of bridge construction with MSS based on basic
Pre-camber setting principle and method, which has been proved effective in the bridge approach
of Sutong Yangtze River.
Key words:MSS (Movable Scaffolding System)、prestressed concrete、continuous box
girder、alignment control 、pre-camber setting
移动模架逐孔施工方法是利用移动模架造桥机(Movable Scaffolding System,简称 MSS)
进行预应力混凝土连续梁逐孔现浇的一种先进施工方法。由于其具有施工工艺标准化、周期
化、速度快、效益好等优势,在现代桥梁建设中得到了广泛的应用和发展。尤其当墩身较高、
桥址地基软弱或桥下有通车通航要求时,该施工方法具有很大的优越性。
后支点前支点
箱梁悬臂段箱梁现浇段
1 23 4 5 6 施工方向
后导梁承载主梁前导梁
图 1 移动模架法逐孔施工立面简图
移动模架法逐孔施工立面布置如图 1 所示,浇筑每联第一现浇施工跨时,承载主梁支承
于前后两套支撑托架上(支撑托架支承于基础承台或墩柱预留孔);浇筑后续现浇施工跨时,
前支点为支撑托架,后支点通过锚固于门型吊架的钢棒吊起承载主梁(门型吊架搁置于已浇
梁体之上)。
为了施工方便和结构受力有利,一般将施工缝均设在距桥墩 L/5 跨度附近,此处恒载弯
矩接近于零。如图 2 所示,施工缝 A 断面在前期混凝土梁段浇筑结束时处于单悬臂端,竖
向挠度为单悬臂状态的挠度;而在后期混凝土浇筑结束的共同组成体系中,悬臂段梁体位移
作者简