文档介绍:章丘市体育公园东侧旧村改造项目
测
量
施
工
方
案
施工单位:山东电力建设第二工程公司
编制时间:2016年5月24日
目 录
1、编制依据 ······························································1
、章丘测绘站提供的控制点测量报告 ······································1
、施工图纸 ···························································1
、主要规范、规程 ····················································1
2、工程概况 ······························································1
3、施工测量部署 ···························································1
、测量施工的组织结构设置 ·············································1
、测量仪器及工具配置 ················································2
、测量工作的组织措施 ················································2
4、施工测量前期的准备工作 ················································3
、施工测量的前期准备工作 ·············································3
、红点的复测 ·······················································3
、对工程定位桩、水准点的计算与校核要求 ·······························3
、关于对测量中误差的应对措施 ·········································3
5、施工测量放样流程图 ····················································5
6、工程测量规范(GB50026-2007)相关技术要求: ·······························6
7、控制网布设 ······························································6
、建立平面控制网 ····················································6
、高程控制测量 ·······················································7
、平面及高程控制网布设 ·············································7
8、建筑平面控制与地下室施工测量 ············································7
、建筑定位控制的方法 ···············································7
、地下室放线 ······················································7
、地下室施工的高程传递 ············································8
9、对± ············································9
、对地上楼层的平面放线与竖向控制 ·····································9
、关于± ·································10
10、施工测量中的验线工作要求 ············································11
11、沉降观测·················································