文档介绍:现场阀门试压方案 A Plan for Valve Pressure Test on Site Designed by: 编制: Date :日期: Reviewed by: 审核: Date :日期: Approved by: 批准: Date :日期: 目录 Contents 一、目的 Purpose 二、范围 Scope of work 三、参考文件 Reference 四、阀门试压工作流程 The work flow of valve pressure test 五、阀门入库的检查 Inspection of valves upon entry into warehouse 六、试压平台制作 Fabrication of pressure test platform 七、阀门试压 Valve pressure test 八、人员、材料、设备清单 List of personnel, materials, and equipment 九、施工安全 Safety of construction activities 一、目的 Purpose 本程序叙述 XXXX 项目安装工程中阀门现场试压及管理的方法。 T his plan defines the method and management of the valves pressure test on site for XXXX project. 二、范围 Work of scope 本程序适用于 XXXX 项目安装工程所有的管道阀门。 T his plan is applicable to the pressure test work of all piping valves within the scope of installation project of XXXX 三、参考文件 Reference 工艺管道布置图,单线图及工艺管道系统流程图( PID ) Process piping layout drawing, isometric drawings & PID. 《工业金属管道工程施工及验收规范》 GB50235-97 《 Construction & acceptance code for industrial metallic piping project 》 GB50235-97 《石油化工有毒可燃介质管道工程施工及验收规范》 SH3501-2002 《 Construction & acceptance code for project of petrochemical piping with poisonous, flammable media 》 SH3501-2002 四、阀门试压工作流程 The work flow of valve pressure test 阀门入库的检查阀门入库试压平台制作阀门试压合格阀门内部吹干、密封试压合格阀门标识存放 Valves inspection upon warehouse entry----> warehouse entry----->fabrication of pressure test platform---->valves pressure test----> purge