文档介绍:1 109 QUEST Work packages are used to:
1 109 A Represent units of work at a level where work is performed.
1 109 B Clearly distinguish one work package from all others assigned to a single functional group.
1 109 C Limit the work to be performed to relatively short periods of time.
1 109 D All of the above.
1 109 E A and B only
1 109 D
1 108 QUEST Project life cycles are very useful for _____ and _____ .
1 108 A Configuration management, termination
1 108 B Objective setting, information gathering
1 108 C Standardization, control
1 108 D Configuration management, weekly status updates
1 108 E Approval, termination
1 108 C
1 107 QUEST Which of the following are included as part of a scope statement?
1 107 A Project justification
1 107 B Project deliverables
1 107 C Project objectives
1 107 D All of the above
1 107 E B and C
1 107 D
1 106 QUEST The initial document that formally recognizes the existence of a project is the _____ .
1 106 A Scope baseline
1 106 B Management plan
1 106 C Project charter
1 106 D Configuration control report
1 106 E None of the above
1 106 C
1 105 QUEST Which of the following is not a scope management process?
1 105 A Initiation
1 105 B Scope planning
1 105 C Scope Definition
1 105 D Scope change control
1 105 E Scope verification
1 105 D
1 104 QUEST In which of the following scope management processes is the scope management plan prepared?
1 104 A Initiation
1 104 B Scope planning
1 104 C Scope Definition
1 104 D Scope change control
1 104 E Scope verification
1 104 B
1 103 QUEST The project charter is prepared in which scope management process?
1 103 A Initiation
1 103 B Scope planning
1 103 C Scope Definition
1 103 D Scope change control
1 103 E Scope verification
1 103 A
1 102 QUEST The work breakdown structure (WBS) is first developed in which scope management process?
1 102 A Initiation
1 102 B Scope planning
1 102 C Scope change c