文档介绍:企业工法通风与空调作业指导书/GJ-25-2005 1 of 4 (二).通风设备安装 Purpose and applicable scope 本作业指导书叙述了空气处理机组的安装步骤和技术要求,以指导安装作业,保证安装质量,本指导书适应于空气处理机组(热送风机组、排风机组、空调机组、循环冷风机组、及小型分体空调器)安装。 This construction plan isintended todescribe installation procedure and technical requirement ofHVAC unit toensure quality ofinstallation. This construction plan isapplicable ofinstallation ofHVAC unit such asblower unit, exhaust cleaning unit, circle cooling wind unit and small air-condition unit. 2. 工作内容及操作流程 work flow 技术交底 technical orientation 运输设备到安装现场 equipment transport to site 基础上放线 setting out on foundation 施工准备 preparation 审图 review of drawing 设备开箱检查 inspection of unpacking 基础检查和验收 acceptance & transfer of foundation 安装就位 location of equipment 企业工法通风与空调作业指导书/GJ-25-2005 2 of 7 3. 操作程序及技术要求: operation procedure & technical requirement precondition a)有关设备安装的施工图纸和技术文件完整。 Shop drawing &technical document oninstallation should beprovided fully. b)有关人员熟悉图纸和相关的技术文件。 Relevant personnel should understand drawing &relevant technical document. c)安装现场清理干净,安全可靠,具备安装条件。 Site should becleaned, safety and isapplicable ofinstallation. d)设备安装基础经过检查验收合格。 Thefoundation ofequipment should bechecked and accepted. e)所用的吊装和运输设备完好,所需工机具完好。 Allequipment &tools that used for lifting &transporting should beingood condition. f)对吊装不锈钢设备,所用绳索要采取保护措施。 Allslings that used for lifting stainless steel equipment should beprotect