文档介绍:Date : Proposal : KAYA/YO/071210A Item Description Qty Unit Unit Rate Amount (RMB) 1. Main Construction Preliminaries 准备工作 Site Preparation & setting . ¥600 ¥600 场地准备放线 General cleaning & debris removal daily. 1no. ¥900 ¥900 每日垃圾清运 Protection & cleaning. 1no. ¥900 ¥900 现场保护和清洁 Insurance by contractor. 1no. ¥1,200 ¥1,200 工程保险 Connection to temporary power supply 1no. ¥600 ¥600 临时电接驳 . 6 Demolition Fee for existing partition. 1no. ¥800 ¥800 原有隔墙拆除 Sub - total¥5,000 Partition and Associated works 间墙及相关工作 Supply & install 100mm thick single layer gypsum board partition .11m2¥145 ¥1,595 供应及安装 100mm 石膏板间墙 Sub - total¥1,595 Wall Finish 墙面 Supply and install emulsion paint finish to partition. 22m2¥55¥1,210 墙面批灰连乳胶漆 Supply & install wallpaper. 22m2¥145 ¥3,190 提供及安装墙纸 Sub - total¥4,400 1 Description Qty Unit Unit Rate Amount (RMB) Ceiling finishes 天花 epair the ceiling system 1 sum ¥1,200 ¥1,200 原有天花板修复 Sub - total¥1,200 Floor 地面 Supply & install wood floor 10m2¥560 ¥5,600 提供及安装防静电地板 Sub - total¥5,600 2. Electrical System 机电系统 Supply and ins