QUESTION 1:
Which of the following represents the BEST process to plish resource planning?
A. Identifying the required resources in the project charter
B. Identifying the available resources and allocate them to all activities in the current phase of the
project.
C. Identifying the required resources and allocate them to all project activities.
D. Identifying the resources that performed past similar projects, and allocate them to all project
activities
of the above
Answer: C
QUESTION 2:
When preparing the probability distribution of cost es for a project, what is the
estimate with a 15% probability of being exceeded approximately one standard deviation
___________?
A. Above the mean.
B. Below the mean.
C. Below the median.
D. Above the median.
Answer: A
QUESTION 3:
What would be the cost performance index if
BCWP =350, ACWP = 400, and BCWS = 325?
Note:Budgeted Cost of Work Performed (BCWP),
Actual Cost of Work Performed (ACWP) and
Budget Cost of Work Schedule (BCWS)
Answer: D
QUESTION 4:
Which technique would you be using if you analyze which sequence of activities has the
least amount of flexibility when you need to predict project duration?
path
- The Power of Knowing
PMI-001
diagramming
chart
Carlomethod
Answer: A
QUESTION 5:
Taking the following table into account, where would corrective action be MOST effective
when you make use of Pareto's Rule?
Origin of Problem Percent of Problems
Design 60
Development 15
Prototype 10
Testing 10
Fabrication 5
Answer: D
QUESTION 6:
Which of the following describes Fast Tracking?
loophol