文档介绍:三峡新能源傅村50MW光伏发电项目







中州建设有限公司三峡微山光伏项目部
2017年 12月7日
三峡新能源傅村50MW光伏发电项目
脚手架施工方案
审批页
编制人:
审核人:
审批人:
目录
一、工程概况····································································1
二、编制依据···································································1
三、满堂脚手架构造选择··························································1
四、搭设要求····································································1
1、脚手架材料选择····························································1
2、满堂脚手架施工措施·······················································1
3、步架······································································2
4、支撑脚手架计算书··························································2
5、满堂脚手架搭设顺序······················································10
6、脚手架的拆除····························································10
一、工程概况
本工程为三峡新能源傅村50MW光伏发电项目(升压站),桩基础(HPC-400(95)AB-C80-12、7、HPC-400(95)AB-C80-12、7)桩,桩顶为承台基础,上部为框架结构梁、板,混凝砼为C30。
二、编制依据
《建筑施工扣件式钢管脚手架安全技术规范》(JGJ130-2011)
《混凝土结构设计规范》GB50010-2010
《建筑结构荷载规范》(GB50009-2012)
施工组织设计及施工图纸。
三、满堂脚手架构造选择
横向间距或排距(m):;纵距(m):;步距(m):;
采用的钢管(mm):Φ48× ;
扣件连接方式:单扣件,考虑扣件的保养情况,扣件抗滑承载力系数:;
四、搭设要求
1、脚手架材料要求
、,其力学性能应符合国家现行标准《碳素结构钢》GBT700中Q235A钢的规定,用于立杆、大横杄、斜杆的钢管长度为4-6米,小横杆、-,使用的钢管不得有弯曲、变形、开焊、裂纹等缺陷,不合格的钢管决不允许使用。
,并持有产品合格证,扣件锻铸铁的技术性能符合《钢管脚手架》GB15831-1995规定的要求,对使用的扣件要全数进行检查,不得有气孔、砂眼、裂纹、滑丝等缺陷。扣件与钢管的贴合面要严格整形,保证与钢管扣紧的接触良好,扣件夹紧钢管时,开口处的最小距离不小于5mm,扣件的活动部位转动灵活,旋转扣件的两旋转面间隙要小于1mm,。
,×.
×。
××。
,固定点应牢固可靠。
2、满堂脚手架施工措施
结合本工程结构形式、实际施工特点,室内采用满堂脚手架模板支撑体系来满足梁、板
的施工。
。,因此必须保证其整体性和抗倾覆性。

,西面、北面、东面立杆下垫250*1500钢铁模其他部位垫250*300垫木并加设扫地杆。
:四边连续设