文档介绍:Syska Hennessy Group Cleveland Clinic New Data Center Issue for Permit/Construction
CLE09001 Brecksville, Ohio September 3, 2010
SECTION 230900 – INSTRUMENTATION AND CONTROL FOR HVAC
PART 1 - GENERAL
RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General Requirements Division 01,
Division 23 Specification Sections, mon Work Requirements for HVAC apply to the
work specified in this Section.
1. Summary
a) The Building Management System (BMS) sub-contractor is responsible to provide
and install all control and monitoring devices to provide plete system. The
BMS Contractor shall provide plete system consisting of Direct Digital
Control Panels (DDCPs), field I/O devices, power supplies and supportive
software, to meet the written sequences of operations, as written in contract
specifications. The system shall munications to DDCP’s, and provide
operator interaction, data consolidation and global control functions via a Local
work (LAN) or Wide work (WAN) communication link
backbone.
b) The BMS Contractor shall install the work for the
facility. Work shall include HVAC control, energy management, alarm
monitoring, point trending, point reporting and maintenance management
functions. Coordinate with all site low voltage systems as specified.
c) All labor, material, equipment and software not specifically referred to herein or on
the plans, that is required to meet the functional intent of this specification, shall be
provided without additional cost to the Owner.
d) The BMS Contractor shall be a sub-contractor to the mechanical contractor and
shall assign a BMS Contractor that meets or exceeds “BMS Contractor Installer
Qualifications paragraph.”
e) Refer to “Scope of Work” paragraph for additional information.
RELATED SECTIONS
A. Division 23 - Mechanical Section
B. Division 26 - Electrical Section
ABBREVIATIONS
A/C - Air Conditioning