文档介绍:北环东延线塑料排水板软基处理施工方案
----------------------------------------------------------------------------------------------..................................................... 9
................................................................................ 9
.................................................................. 11
.............................................................................. 12
...................................................................................... 13
------------------------------------------------------------------------------------------------
——————————————————————————————————————
............................................................................. 13
六、确保工程质量和工期的措施 .................................................. 14
塑料排水板技术保证措施 ......................................................... 14 1
开平市环城公路北环东延线一期工程 排水板及堆载预压施工方案
管理质量保证措施 ..................................................................... 15
工期保证措施 ............................................................................. 17
七、排水板施工平安措施 ............................................................. 20
2
------------------------------------------------------------------------------------------------
——————————————————————————————————————
开平市环城公路北环东延线一期工程 排水板及堆载预压施工方案
一、工程概况
本工程为北环东延线一期新建道路,按照图纸设计进行打塑料排水板进行软基处理,总工程量为342273米,采用SPB-B型塑料排水板。
施工参照标准及标准
?塑料排水板施工规程?(JTJ /T 256-96)
?塑料排水板质量检验标准?(JTJ/T257-96)
?公路路基施工技术标准?(JTG F10—2022)
开平市环城公路北环东延线一期工程设计施工图
公路工程质量检验评定标准
3
开平市环城公路北环东延线一期工程 排水板及堆载预压施工方案
二、施工布置
为按要求按时按质按量地完成施工任务,我公司将派出具有丰富的施工管理经验的人员参与本工程的施工管理和优良的施工机具参与施工,同时在资金和后勤等方面做好工程的效劳工作。管理机构图如下所示: