文档介绍:辛集化工整体搬迁项目工程
75t/h锅炉工程
钢构造施工
专
项
施
工
方
案
编 制 ···········································································20
钢构造吊装········································································································································26
钢构造安装········································································································································27
辅钢结安装········································································································································27
钢梯、钢栏杆施工措施及制作工艺····························································································28
1#、2#输煤栈桥·······························································································································31
钢构造涂装········································································································································38
钢构造验收········································································································································
39
重要技术组织措施···························································································································40
安全施工保证····································································································································42
钢构造施工应急预案·······················································································································53
工期保证体系····································································································································60
一、工程概况
工程名称: 辛集化工整体搬迁工程
建设单位: 昊华辛集化工有限责任公司
设计单位: 山东奥翔电力设计院
监理单位: 长沙华星建设监理有限公司
施工单位: 北京城建建设工程有限公司
本工程构造为钢筋混凝土框排架构造,构造设计使用年限为50年。建筑抗震设防类别为丙类建筑,建筑构造安全级别为二级,地基基本设计级别为丙级。
75t/h锅炉工程分为-----化水车间、主厂房、碎煤楼、1#、2#栈桥、空压机房、变频器室、脱硫综合楼等单位工程。
其中化水车间、1#、2#栈桥、脱硫综合楼均有钢构造,化