文档介绍:PMBOK指南(第5版)第四章****题(附答案)
stakeholder has a reputation for making many changes on projects. What is the best approach a project manager can take at the beginning of the project to manager this stituation?
A. Say “no” to the stakeholder a few times to make him change his habits.
stakeholder involvement in the projects as early as possible.
to the stakeholder’s boss to find ways to direct the stakeholder’s activities to another project.
D. Ask that the stakeholder not be included in the stakeholder listing.
1. 有一位项目干系人是因经常进行项目变更是出了名的。在项目开始时,项目经理最好是采取什么方法来管理这种情况?
A. 对这位干系人说几次“不”,使他改掉他的****惯
B. 尽可能早地让这位干系参与到项目中
C. 和这位干系人的老板商量办法,把他调到其他项目
D. 要求别把这位干系人列入干系人名单
2. Which project management process group defines and authorizes the project?
A. Planning
B. Monitoring and Controlling
C. Initiating
D. Executing
2. 哪个项目管理过程组确定并且核准一个项目?
A. 规划
B. 监控
C. 启动
D. 执行
is done by:
A. Senior management
B. Project team member
C. Project management consultant
D. Project manager
3. 整合由__________来做。
A. 高级管理层
B. 项目队伍成员
C. 项目管理顾问
D. 项目经理
4. The most important role of PM in a anization is?
A. Communication
B. Integration
C. Negotiating
D. Leadership
4. 项目经理在矩阵组织中最重要的角色是?
A. 沟通
B. 整合
C. 谈判
D. 领导
technical work pleted on the project. Which of the following remains to be done?
A. Project budget
B. Risk management plan
C. Staff management plan
D. Lessons learned
5. 项目所有的技术工作都已完成,下面哪项是接下来要做到的?
A. 项目预算
B. 风险管理计划
C. 职员管理计划
D. 经验教训总结
6. Which of the following is true regarding constraints and assumptions?
A. Constraints restrict the actions of the project team, and assumptions are considered true for planning purposes.
B. Constraints are considered true for planning purposes, and assumptions limit the options of the project team.
C. Constraints consider vendor availability and resource availability to be true for planning purposes. Assumptions limit the project team to work within predefined budgets or time l