文档介绍:目录
第一节临时施工用电
一、设计依据······················································3
二、概况··························································3
三、现场勘察及初步设计············································5
四、负荷计算······················································5
五、变压器及高低压侧母线和开关的选择······························9
六、安全用电技术措施··············································9
七、安全用电防火措施··············································10
八、施工现场临时用电安全规定动····································11
九、施工现场安全用电机具操作管理措施······························11
十、安全用电十大禁令··············································13
第二节临时施工用水
一、概况··························································14
二、施工用水量计算················································14
三、施工机械用水量················································15
四、施工现场生活用水量············································15
五、生活区生活用水量
··············································16
六、消防用水量····················································16
七、总用水量计算··················································16
八、水源选择······················································16
九、水泵的选择····················································16
十、供水管道布置··················································17
十一、贮水池和化粪池的设计··········································17
十二、消防给水······················································
17
十三、施工临时排水··················································17
第一节临时施工用电
一、设计依据
设计依据主要包括以下规程规范及资料:
(1)《建筑工程施工现场供用电安全规范》GB50194—93;
(2)《施工现场临时用电安全技术规范》JGJ46—2005;
(3)《低压配电设计规范》GB50054—95;
(4)《供配电系统设计规范》GB50052—95;
(5)《通用用电设备配电设计规范》GB50055—93;
(6)甲方提供的现场电源资料;
(7)现场临时用电设备负荷和配置资料;
二、概况
本工程现场临时用电系统,根据JGJ46-88临时用电规范而设计。根据表内临时用电设备负荷统计,,计算容量256KVA。(将视在负荷换算到有功负荷,,。)甲方宜提供320千瓦,方可满足施工用电要求;另自备120KW柴油发电机一台;为确保施工用电可靠,合理节约能源。在供电结构上合理安排。加强管理。
施工现场用电统计如下:
序号
设备名称
规格型号
安装功率KW
数量
合计功率
备注
1
弯铁机
GJ7—40
5
2
10
2
钢筋调直机
GJ—14/4
1
3
截铁机
GJ5—49—1
5
2
10
4
交直流焊机
BX1—250
21
2