文档介绍:目录
1、工程概况·················································2
2、编制依据·················································2
3、施工前准备···············································3
4、冷箱钢结构安装程序·······································4
5、施工方法、技术措施·······································4
6、脚手架的搭设和拆除·······································9
7、质量控制措施
············································12
8、施工进度计划············································12
9、工程质量控制措施·······································13
10、职业安全卫生与环境管理································14
11、现场平面布置图··········································14
12、附:100T履带吊车性能表及吊蓝使用方法···················15
冷箱结构安装施工方案
1、工程概况
本空分装置的规模为52000Nm3/h,主要设备由林德公司提供。根据本次招标文件提供有关设备说明,同时结合我公司根据承担同类工程的施工经验,冷箱钢结构为模块式设计,现场组装,因此冷箱板
到达现场应为预制成形的结构片、以及梯子、平台、设备支架、管架及阀架等,需要现场组装,现场进行螺栓联接和焊接。
空分冷箱设备是该装置的关键设备之一,设计由德国LINDE公司负责。本工程冷箱结构由两个冷箱组成,即ND主冷箱,EA换热器冷箱,材质大部分为碳钢,。其外形尺寸如下:
ND主冷箱
EA换热器冷箱
10060*6540*55200
12840*7040*18370
,冷箱施工有如下特点:
,拼装时占地面积大,垂直高度要求高,空中组对施工难度大。
,焊缝要求美观,焊缝外侧打磨平整,焊接变形量大,需要采取一定的防变形措施。
,吊车站位时间长。
,箱内塔、容器,管道密集布置,箱内施工作业狭窄,高空作业多,箱内施工必须要周密安排。
冷箱的安装应与冷箱内设备的安装交叉进行,施工中应做好工序安排,加强协调,并注意安全防护和施工成果保护,确保冷箱和设备的施工安全和质量。
:
同类工程施工经验
《钢结构工程施工及验收规范》——GB50205-2001
《钢结构焊接规程》——JGJ81-91
《作业平台钢梯及栏杆》——JSJT-90
《石油化工施工安全技术规程》SH3505-2001
《大型空分设备安装技术要求》——HTA1107-93
:
施工前应仔细认真熟悉图纸,并对施工班组进行工程技术交底。
施工前,所有参加施焊的焊工必须有相应的焊接合格证。
施工方案已批准。
:
冷箱钢结构安装前,应对土建基础进行全面彻底的检查,并及时办理中间交接验收记录。
基础验收时,应认真检查下列各项应符合要求:
a、基础周围回填夯实完毕。
b、基础混凝土强度达到设计要求。
c、基础支承面、地脚螺栓的验收技术要求如下表:
项目
允许偏差(mm)
基础支承面
标高
±3
水平度
1/1000 全长≤10mm
平面度
2/1000
预埋地脚螺栓
螺栓中心偏移
5
螺栓外露长度
+20
螺纹长度
+20
:
进场的所有材料及联接螺栓应具有质量证明书。
、弯曲、扭曲等缺陷。
钢材的表面应无麻点,锈蚀或划痕等严重缺陷。
本工程中有不少不锈钢结构支架,材料的堆放要分门别类,碳钢与不锈钢不能堆放在一块。
冷箱板验收应符合下表要求
尺寸
公差带
大于
至
1000
2000
±3
2000
4