文档介绍:靖江龙威粮油工业有限公司油罐安装工程
施工组织设计
编制:_________
审核:_________
监理审核:_________
业主代表审核:_________
业主总工批准:_________
辽宁石化安装有限公司
目录
1、编制说明及编制依据.........................................3
.................................................3
.................................................3
.................................................3
2、施工管理目标...............................................3
.................................................3
.................................................3
.................................................4
3、项目管理组织机构及职责.....................................4
.............................................4
.................................................4
4、施工技术方案...............................................7
.............................................7
.............................................9
.............................................16
.............................................28
.........................................33
.........................................34
5、工程质量保证措施...........................................42
6、施工机械的进场计划.........................................53
7、施工进度计划...............................................54
8、劳动力计划.................................................60
9、安全施工措施...............................................60
10、工程管理与施工配合措施....................................69
11、现场文明施工措施..........................................81
12、临时设施计划..............................................83
工程名称:江苏靖江龙威粮油工业有限公司一期工程
工程地点:靖江粮食产业园区
工程范围:油罐安装工程
(1)24台储罐设备制作、安装;
(2)甲供安装主材,安装辅材及机具乙方自理;
化工建设项目施工组织设计标准HG20235-93
相关的国家标准规范
1)总目标:工程质量合格,确保达到省部级优质工程标准
2)单位工程质量合格率:100%
3)单位工程优良率: 安装工程>95%
4)焊接一次合格率: 98%以上
5)重大质量事故: 0
6)施工将严格按照现行国家及行业的施工及验收规范、施工图纸的技术要求、质量标准进行施工。
总工期:90天
储罐制作开工日期:20