文档介绍:武汉大道跨铁路桥下横梁塔梁混凝土施工关键技术
【摘要】本文结合武汉大道跨铁路桥工程下横梁塔梁混凝土浇筑方案,通过设计计算,较好地解决了主塔塔梁混凝土二次浇筑施工中存在的问题,对类似横梁施工具有一定的借鉴和参考意义。
【关键词】斜拉桥;塔梁;施工方案;二次浇筑及张拉;支架设计;关键技术
wuhan road railway bridge beams across the beam concrete tower key technologies
chen kai—qiao1,she shao—bin2,wang ji—lian1,mao wei—qi1
( railway bridge bureau group co., ltdwuhanhubei430050;
construction design divisionwuhanhubei430050)
【abstract】in this paper, cross the railway bridge in wuhan avenue beams under the concrete pouring tower beam program, through the design and calculation, solved the main tata second pouring of concrete beam construction problems, construction of a similar beams with a certain sense of reference and reference .
【key words】cable—stayed bridge;tower beam;construction program;secondary placement and tension;stent design;key technology
1. 工程概况
(1)武汉大道是武汉市汉口地区南北向重要的城市快速路,是联系城市一环线、二环线、三环线的放射线和快速出城通道;跨铁路桥为主跨138m,边跨(81+41)m的独塔双索面预应力混凝土箱梁斜拉桥,上跨金桥大道及京广、合武等12股道铁路线,是武汉大道的控制性工程。主塔顺桥向为柱式结构,横桥向为“a”型,:1,钢筋混凝土结构,,,主梁右幅截面不变,左幅截面高度线性变化,两个边箱宽度不变,横向尺寸通过调整横梁的跨度加以实现。
图1武汉大道跨铁路桥桥式布置图
图2横梁断面及预应力钢束布置
(2)下横梁及塔梁固结段为预应力混凝土结构,双层箱型截面,横跨金桥大道节段长42m,宽21m,在金桥大道现状道路上空约15m,,%横坡,混凝土方量为2303m3,横梁设54束纵向预应力钢束。横梁断面及预应力钢束布置如图2所示。
2. 横梁及塔梁固结段施工方案
(1)跨铁路桥工程主塔下横梁及塔梁固结段设计要求采用一次浇筑一次张拉工艺,采用支架法现浇施工。横梁箱室达16个,为便于施工及质量控制,确定采用两次浇筑及两次张拉工艺,,第二次浇筑高度