文档介绍:Testing: Unit Testing / User Manual Module : Production & Planning
ENVIRONMENT
SYSTEM : SAP R/3 ECC
CLIENT : 200
UNIT TESTING SCENARIO
SCENARIO NUMBER : PP01-05
DESCRIPTION :Create Production Order
PREPARED BY
NAME :ASCS
DATE :
TEAM : Production Planning
APPROVED & TESTED BY
NAME : Nanhe Babu (PwC)
DATE :
TEAM : Production Planning
Page 1 of 8
Testing: Unit Testing / User Manual Module : Production & Planning
1. Transaction Code/ Path
Menu
Path
MD04
2. Input Data
Page 2 of 8
Testing: Unit Testing / User Manual Module : Production & Planning
Description of the Nature of the
Value of the Field
Field Field
Material Mandatory Input the material no.
MRP Area Optional
Plant Optional
Press on Tab
OR PRESS ‘ENTER’
The following screen is displayed.
Double click on Planned order which you want to convert into Production order.
Page 3 of 8
Testing: Unit Testing / User Manual Module : Production & Planning
Additional data screen is displayed.
Press Prod. Ord soft key
Click '→ PartConvProdOrder' key for converting Partial conversion of Planned Order Quantity.
After clicking Partial Conversion, the quantity will be changed to actual Production Order quantity,
which needs to be produced depending upon availability of actual Quantity.
Page 4 of 8
Testing: Unit Testing / User Manual Module : Producti