文档介绍:金牛区互助村片区拆迁
安置房工程
土方开挖专项
施工方案

四川省佳宇建筑安装工程有限公司
2013年6月
目录
第一章工程概况····························································3
第二章编制依据····························································4
第三章施工部署···························································4
第四章施工方法····························································6
第五章基坑施工现场管理···················································8
第六章施工质量及保证措施··················································9
第七章安全文明施工措施···················································10
、安全施工措施························································10
、文明施工措施·······················································11
第八章应急救援预案
·······················································12

土方开挖施工方案
第一章工程概况
、工程概述
**********工程项目位于成都市城西北部分,金牛区内,地处三环附近,金周路地铁站旁。由1~7号高层塔式及单元式住宅组成,其中地下室一层汽车库(局部两层),地上建筑为11~15层,总建筑面积约为19万平方米。(见下表):
幢号
建筑层数
建筑高度
建筑面积
结构形式
1#
地上15层,地下1层
M

剪力墙
2#
地上15层,地下2层
M

剪力墙
3#
地上15层,地下2层
M

剪力墙
4#
地上15层,地下2层
M

剪力墙
5#
地上12层,地下1层
M

剪力墙
6#
地上15层,地下1层
M

剪力墙
7#
地上15层,地下1层
M

剪力墙
地下室(人防)
地下一层(局部两层)
约56000㎡
框架
、工程地质和水文地质
本工程场地及周边地区地势较平坦、开阔,不会发生滑坡及地面坍陷等不良地质作用。地貌单元属于成都平原岷江水系一级阶地。根据勘察野外鉴别、室内土工试验及原位测试综合分析,场地勘探深度内的地基土可分为以下两个工程地质层:1、第四系全新统人工填土层(杂填土、素填土);2、第四系全新统冲击层(粉质粘土、粉土、细砂、中砂、松散卵石、稍密卵石、中密卵石、密实卵石)。土质分布详见该工程地勘报告。
、施工场地条件
本工程位于成都市金牛区互助村,金周路地铁站旁。拟建场地主要为农田和房屋拆迁区,场地地形平坦。但规划红线距地下室剪力墙较近。场地东、南、西三面红线外均为规划道路,还未修建。北面为小河流经,河宽约4m常年有水。小河局部距地下室边线较近。施工难度较大。金周路到施工现场主要道路为东面一条3m宽农村机耕道。经初步勘探,基础开挖区域无市政主要管、线。
、基坑安全等级及基坑支护
根据地勘报告显示,该工程基坑安全等级为二级。~,总土方开挖量约为36万立方。由于基坑整体开挖过程中,边坡壁在自然状态下不能保证稳定,所以开挖时必须采取适当的支护措施,以确保基坑壁稳定和施工安全。,。故该工程属于深基坑,根据《成都市建筑工程深基坑施工管理办法》要求,该工程基坑支护需经过专家论证。目前,该工程基坑支护方案已通过专家论证。场地北侧因有小河流经过且离基坑较近,故设计为护壁桩支护,其余部位采用土钉墙喷锚支护。详见该工程《基坑支护专项施工方案》,后附土方开挖支护平面布置图。

因该工程地处成都市三环路外侧金周路地铁站旁,周围无土方堆场。经建设、监理、过控施工等单位实地考