文档介绍:预压装配式预应力混凝土结构的研究与应用
董荣书1 屈克达2 高莺燕3
(,贵州贵阳 550008;,河南洛阳 471003;,贵州贵阳 550000)
摘要:预压装配式预应力混凝土结构经过预应力筋的张拉预压,克服了装配式结构难以装配、节点连接性差的缺点,国内外研究表明:预压装配式结构具有良好的抗震性能,能够满足地震区建筑“强柱弱梁”“强节点弱构件”的抗震理念,具有良好的发展前景。
关键字:预压装配式框架;抗震性能;发展前景
中图分类号: 文献标志码:A
Research and Application of Pre-stressed Pre-cast Concrete Frame
DONG Rong-shu 1 QU Ke-da2 GAO Ying-yan3
(1. Guizhou Vocational and Technical College munications, Guiyang, 550008, China;2. China Machinery TDI International Engineering .; Luoyang 471003, China;3. Guiyang Highway Bridge Engineering pany, Guiyang, 550000, China)
Abstract:Pre-stressed Pre-cast Concrete (PPC) frame can e ings such as difficult to assemble、poor reliabilities of node connections by stretching pre-stressed bars . Studies show that PPC has better seismic performance. The “strong column and weak beam”“strong connection ponents” design requirements can be satisfied. It has good prospects for development.
Key words:pre-stressed pre-cast concrete frame;seismic performance;development prospect
0 引言
预压装配式预应力混凝土结构是在工厂生产预制梁、柱等构件,养护完成后运至施工现场吊装,通过预制梁中预留的孔洞穿拉预应力钢筋,使梁柱结合为整体受力体系[1]。它将预应力技术应用于装配式结构当中,不仅解决了装配式结构难以装配的问题,而且克服了装配式结构节点连接可靠性差的缺点,能够满足“强柱弱梁”“强节点弱构件”的设计要求[2],推动了装配式结构在地震区的应用。
1 预压预制装配式结构的特点
生产过程
预压装配式预应力混凝土框架梁柱节点的连接技术主要源自于日本的“压着工法”[3]施工技术,如图1所示,先把梁进行一次张拉,运至施工现场吊装完成后,在梁柱预留孔洞中穿预应力筋,实施二次张拉预压,使之形成整体受力体系。这样,预应力筋既可以作为施工时