文档介绍:Technical Report Documentation Page
1. Report No. 2. Government Accession 3. Recipient’s Catalog No.
FHWA/TX-05/9-580/589-1 No.
4. Title and Subtitle 5. Report Date
PRODUCTION AND QUALITY CONTROL OF HIGH December 1998
PERFORMANCE CONCRETE IN TEXAS BRIDGE 6. anization Code
STRUCTURES
7. Author(s) 8. anization Report
John J. Myers and Ramón L. Carrasquillo No. 9-580/589-1
9. anization Name and Address 10. Work Unit No. (TRAIS)
Center for Transportation Research
The University of Texas at Austin 11. Contract or Grant No.
3208 Red River, Suite 200 9-580 and 9-589
Austin, TX 78705-2650
12. Sponsoring Agency Name and Address 13. Type of Report and Period
Texas Department of Transportation Covered
Research and Technology Implementation Office Technical Report (9/96 — 8/97)
. Box 5080 14. Sponsoring Agency Code
Austin, TX 78763-5080
15. Supplementary Notes
Project conducted in cooperation with the Federal Highway Administration.
16. Abstract
To demonstrate the suitability of using high performance concrete (HPC) in highway structures, the FHWA
initiated a series of projects in 1993 that included plete incorporation of HPC — from design to long-term
monitoring of the bridges in service. The report focuses on the design and construction of the first two of these
projects in the United States, namely, the Louetta Road Overpass in Houston, Texas (Research Study 9-580), and
the North Concho River Overpass in San Angelo, Texas (Research Study 9-589).
This report summarizes the observations of, and conclusions obtained from, both laboratory and field
investigations related to these two HPC bridges. It investigates HPC properties, mix design, applicability of
current design requirements, applicability of current construction practices, predictability of short- and long-term
performance, and the requirements for quality control and quality assurance testing and inspection. The
performance-related test re