文档介绍:PSS
Asia Pacific
TQM OQC
August 2005
Quality Report wk33Tai Sing
1. Quality Raw Data
Please click the below attached excel doc. and see the raw data.
The raw data from subcontractor need to be confirmed further because there is some confusion which need to be clarified. That is in which way the reworked lot is showed “pass”.
2. Data Analysis
The Quality Performance For The Total.
LAR
*% PQC (N/A)
65% FQC
73% PSS OQC
75% MQA
The Quality Performance For The Total.
% / PPM
% / 630,000 PQC
% / 36,000 FQC
% / 23,000 PSS OQC
% / 39,000 MQA
2. Data Analysis
2. Data Analysis
Defects Distribution with Pareto Chart and 80:20 Principle.
PQC
2. Data Analysis
Defects Distribution with Pareto Chart and 80:20 Principle.
FQC
2. Data Analysis
Defects Distribution with Pareto Chart and 80:20 Principle.
PSS OQC
2. Data Analysis
Defects Distribution with Pareto Chart and 80:20 Principle.
MQA
2. Data Analysis
The Result.
From the PQC data, we are surprised to find that the function failure takes % which is serious problem.
The dirty parts, cloth torn, scratch and rattling take the most of the failure.
The attention should be paid because there is parts m