摘要:预应力管桩可分为后张法预应力管桩和先 张法预应力管桩。因其造价低,施工速度快,可以节约施工 周期,加快项目的建设等优点,被广泛应用于工业、房建、 高速铁路、高速公路和民用设施工程中。本文在对预应力管 桩断桩事故类型的分析基础上,提出了改善和预防预应力管 桩断桩的一些可行性建议,具有一定的参考实践价值。
关键词:预应力管桩,断桩,地质,焊接质量,土 方回填
Abs trac t: pres tressed pipe pile can be divided into t his met hod pres tressed pipe pile and firs t pres tressed pipe pile of law. Because of its low cost, and construction speed is quick, can save the construction period, speed up the construction of the project etc, and is widely used in industry, high speed railway, endowed, highway and civil infrastructure. In this paper the breaking pile prestiessed pipe pile are based on the analysis of the accident type, and put forward the improvement and prevent prestressed pipe pile of pile breaking some feasible Suggestions to have the certain reference value of practice.
Keywords: prestressed pipe pile, breaking pile,
geology, and the quality of welding, turkmen backfilling
中图分类号:TU394文献标识码:A文章编号:
1、预应力管桩断桩事故类型
造成预应力管桩断桩的原因是非常多而复杂的,主要有 地质因素、开挖和机械的碾压因素、堆土所产生的挤压力因 素和焊接质量因素等等,下文将对预应力管桩在施工中的典 型断桩成因进行详细分析。
1复杂地质条件引起的断桩
预应力管桩的沉桩主要有锤击沉桩和静压沉桩两种方 式。无论是哪一种沉桩方式,施工单位在施工前,都必须了 解建筑场地的地质条件状况,检查其是否适合管桩,同时还 要查看持力层是否还存在着一些孤石、卵石等障碍物,如果 存在就要及时的清理,切不可盲目的将桩往下打,这样很可 能会造成桩的爆破和断裂。例如,针对桩尖遇到大块砾石而 引起断桩的问题时,就应该先查图纸设计的要求,根据图纸 设计的项目指标,查看桩尖设计的钢板厚度是否满足管桩的 要求,然后再检查在实际施工中是否按照图纸的厚度来加工 桩尖。
1. 2 土方开挖和机械碾压引起的断桩
在完成了预应力管桩的施工之后,项目施工单位就需要 对上层的部分进行开挖,一般情况下,施工单