土建标书样本tenderforstaffquarters
The External Accessory Projects for
ening Record
Appendix II: Clarification Notice
Appendix III:Clarification
Appendix IV: Notice of Award
Appendix V. Notice of the Tendering Result
Appendix VI: Confirmation Notice
Chapter 3 Tender Evaluation Criteria
The Table of the Tender Evaluation Criteria
Tender Evaluation
Evaluation Criteria
Preliminary Evaluation Criteria
Score Components and Criteria
Evaluation Procedures
Preliminary Evaluation
Detail Evaluation
Clarification and Amendment of the Tender Documents
Evaluation Result
Chapter 4 Contract Terms, Conditions and Format
General Provisions
Definitions
Languages
Law
Priority of contract documents
Contract agreement
Drawings and Contractor’s documents
Liaison
Assignment
Prohibition of bribery
Fossils and cultural relics
Obligations of the Tenderee/Employer
Observe law
Issue Notice to Commence
Provide a construction site
Assist the Contractor in applying for certificates and approvals
Organize design presentation
Pay contract price
Organize completion acceptance
Other obligations
Supervisory Engineer .
and Power of Supervisory Engineer
Chief Supervisory Engineer
Supervision personnel
Instructions of the Supervisory Engineer
Contractor .
General obligations of the Contractor
Performance bond
Subcontracting
Consortium
Contractor’s project manager
Management of Contractor’s personnel
Replacement of Contractor’s project manager and other personnel
Guarantee the legitimate rights and interests of Contractor’s personnel
The construction cost shall be used for the specific purpose
Contractor’s survey of the construction site
Adverse material conditions
Materials
Materials provided by the Contractor
Forbid the use of unqualified materials
Construction Equipment and Temporary Facilities