文档介绍:--------------------------校验:_____________-----------------------日期:_____________临时用地复垦方案中铁十二局集团有限公司石长铁路增建第二线站前1标指挥部三项目经理部临时用地复垦方案编制:审核:审批:编制单位:石长铁路增建第二线站前1标三项目部编制时间:二〇一〇年三月编制地点:湖南省常德市德山区目录一、项目简介···············································1二、复垦目标··············································1三、复垦计划安排···········································1四、临时用地情况及相应复垦方案····························21、大临用地·············································22、其它临时用地·········································3五、其它主要保护预防措施··································71、管理措施············································72、地表耕植层存放保证措施································73、节约用地保证措施·····································84、预防土地破坏和环境保护保证措施·························85、复垦保证措施·········································106、质量保证措施··········································107、安全保障措施··········································10临时用地复垦方案一、项目简介1、工程概况+20-32m+4-24m+2-32m+(40+64+40)m连续梁+1-24m。其中特殊桥梁结构主要有一孔49m的槽形梁、跨越堤坝的(40+72+40)m连续梁、跨越沅江的(62+96+96+96+96+92+66)m连续梁、跨越常德大道的(40+64+40)m连续梁。其余均为24米或32米简支T梁。2主要工程数量Φ100㎝钻孔桩基础450根、Φ125㎝钻孔桩基础49根、Φ150㎝钻孔桩基础16根、Φ180㎝钻孔桩基础16根、Φ250承台共102个,墩柱100个。桥台2个,为矩形空心桥台。本管段24m简支T梁10孔,32m简支T梁77孔,49m槽形梁1孔,(40+72+40)m连续梁1联,(62+96+96+96+96+92+66)m连续梁1联,(40+80+48)m连续梁1联、(40+64+40)m连续梁1联,共计101孔。二、复垦目标临时用地使用完后恢复至原有的地形地貌或比原有更改善的状况;恢复原有功能,与周围地形地貌相符。满足复耕要求后,通知土地管理部门会同有关行业管理部门验收,并交付使用。三、复垦计划安排我部于2010年3月中旬开始使用土地进行混凝土搅拌站建设,5月中旬开始使用土地进行便道修整。2011年12月31日工程完工后,开始土地的复垦工作,为了使土地复垦工作顺利、保质完成,我部成立土地复垦工作小组,配备专业技术人员两名、安全工程师一名,环保工程师一名,负责复垦工作,全过程监控,同时配备挖掘机2台、推土机1台、自卸汽车3台、装载机1台、人力30人。在技术、机械、人力、资金各项资源工作全面到位的保证下,复垦工作在2010年6月20日前全面完成。2010年7月前,通知土地管理部门会同有关行业管理部门验收,并交付使用。四、临时用地情况及相应复垦方案1、大临用地砼拌合站搅拌站选址在沅水特大桥小里程侧河堤内平台处62墩附近(DK092+764)。拌合站平均长为120m,平均宽为100m,占地12000m2,料仓占地2500m2,复垦方案:对于拌合站的复垦,应与当地土地部门确定其今后用途,如果留有其用,应给其留下。但是如果必须恢复原状的情况下,我们必须用机械把原来附着在地面的混凝土清理完毕,还应回填种植土,以保证其原始用途,还应充分考虑到其防洪排水的设施,且防洪排水的设施必须与周边的自然水系相结合。2、其他临时用地施工便道设计方案:+4×#、67#、68#、69#墩钻孔桩施工均搭设钻孔平台。平台尺寸为24m×30m。平台采用φ102cm钢管桩做支撑体系,顺桥向贝雷梁做承重梁,横桥向用I45a工字