文档介绍:Exam : PMI-001
Title : Project Management Professional
Ver :
PMI-001
QUESTION 1:
Which of the following represents the BEST process to plish resource planning?
the required resources in the project charter
the available resources and allocate them to all activities in the current phase of the
project.
the required resources and allocate them to all project activities.
the resources that performed past similar projects, and allocate them to all project
activities
of the above
Answer: D
QUESTION 2:
When preparing the probability distribution of cost es for a project, what is the
estimate with a 15% probability of being exceeded approximately one standard deviation
___________?
the mean.
the mean.
the median.
the median.
Answer: A
QUESTION 3:
What would be the cost performance index if
BCWP =350, ACWP = 400, and BCWS = 325?
Note:Budgeted Cost of Work Performed (BCWP),
Actual Cost of Work Performed (ACWP) and
Budget Cost of Work Schedule (BCWS)
Answer: D
QUESTION 4:
Which technique would you be using if you analyze which sequence of activities has the
least amount of flexibility when you need to predict project duration?
path
diagramming
- The Power of Knowing
PMI-001
chart
Carlomethod
Answer: A
QUESTION 5:
Taking the following table into account, where would corrective action be MOST effective
when you make use of Pareto's Rule?
Origin of Problem Percent of Problems
Design 60
Development 15
Prototype 10
Testing 10
Fabrication 5
Answer: D
QUESTION 6:
Which of the following describes Fast Tracking?
loopholes.