1 / 30
文档名称:

Pmi-001 - Pmi Project Management Professional Exam (20060221).pdf

格式:pdf   页数:30
下载后只包含 1 个 PDF 格式的文档,没有任何的图纸或源代码,查看文件列表

如果您已付费下载过本站文档,您可以点这里二次下载

Pmi-001 - Pmi Project Management Professional Exam (20060221).pdf

上传人:bolee65 2014/8/4 文件大小:0 KB

下载得到文件列表

Pmi-001 - Pmi Project Management Professional Exam (20060221).pdf

文档介绍

文档介绍:Exam : PMI-001

Title : Project Management Professional


Ver :
PMI-001

QUESTION 1:

Which of the following represents the BEST process to plish resource planning?
the required resources in the project charter
the available resources and allocate them to all activities in the current phase of the
project.
the required resources and allocate them to all project activities.
the resources that performed past similar projects, and allocate them to all project
activities
of the above

Answer: D

QUESTION 2:

When preparing the probability distribution of cost es for a project, what is the
estimate with a 15% probability of being exceeded approximately one standard deviation
___________?
the mean.
the mean.
the median.
the median.

Answer: A

QUESTION 3:

What would be the cost performance index if
BCWP =350, ACWP = 400, and BCWS = 325?
Note:Budgeted Cost of Work Performed (BCWP),
Actual Cost of Work Performed (ACWP) and
Budget Cost of Work Schedule (BCWS)





Answer: D

QUESTION 4:

Which technique would you be using if you analyze which sequence of activities has the
least amount of flexibility when you need to predict project duration?
path
diagramming
- The Power of Knowing
PMI-001

chart
Carlomethod

Answer: A

QUESTION 5:

Taking the following table into account, where would corrective action be MOST effective
when you make use of Pareto's Rule?
Origin of Problem Percent of Problems
Design 60
Development 15
Prototype 10
Testing 10
Fabrication 5






Answer: D

QUESTION 6:

Which of the following describes Fast Tracking?
loopholes.