文档介绍:PMI New Sample Examination Questions
The following questions are examples of the type of questions that appear on the PMP® Certification Examination.
Disclaimer: These questions are intended for study purposes only. ess on these questions is not indicative of ess on the Project Management Professional Certification Examination. This download of the Sample Exam Questions is for your personal use and NOT mercial use. Any unauthorized use or duplication of this document is prohibited!
1. The MAJOR processes for project integration management are:
A. Project plan development, project plan execution, and overall change control.
B. Project plan development, project plan execution, and scope change control.
C. Project plan development, overall change control, and scope change control.
D. Project plan development, initiation, and overall change control.
2. Project sponsors have the GREATEST influence on the scope, quality, time, and cost of the project during the:
A. Concept phase.
B. Development phase.
C. Execution phase.
D. Close-down phase.
3. Ideally, communication between the project manager and the project team members should take place:
A. Via daily status reports.
B. Through approved documented forms.
C. By written and munication.
D. Through the formal chain mand.
4. A project's payback period ends when:
A. Profit maximum is realized.
B. Unit profit is reali