文档介绍:提高钻孔灌注桩成孔质量

小 组名 称: QC小组
组 长:
发 布 人:
单位(公章):有限公司
20年9月20日
目 录
一、工程概况··················································1
二、QC小组简介·············································2
三、选题理由··················································3
四、现状调查··················································4
五、设定目标··············································
6
六、原因分析及要因确认····································7
七、制定对策··················································13
八、对策实施··················································14
九、效果检查··················································18
十、巩固状况···································20
十一、体会和打算············································21
1
4
1
提高钻孔灌注桩成孔质量
- 1 -

1
一、工程概况
五、设定目标
表一 工程概况表
工程名称
常州市轨道交通2号线一期工程TJ08标文化宫站
工程地点
江苏省常州市
设计单位
常州市上海隧道设计院
建设单位
常州市轨道交通发展有限公司
监理单位
江苏盛华咨询有限公司
开工时间
2016年12月
基础形式
钢筋混凝土钻孔灌注桩
结构类型
钢筋混凝土框架结构
地上层数
0层
地下层数
2层
工程概况
本工程为14m岛式站台地下二层车站,共设置4组风亭、10个出入口,,,~,,,车站结构底板、站台板、中板、%的坡度向下倾斜。~,~,地块内含部分车站出入口、风亭及联络线。其中车站出入口为地下一层,与地块平接;部分风亭为地下两层;~。
钻孔灌注桩施工简介
2号线1、2号坑南侧共计49根钻孔灌注桩,包括37根立柱桩和12根抗拔桩,,桩长20m、35m、40m不等。格构柱规格有4种。其中立柱桩格构柱GGZ1为610×610,角钢为等边角钢200×20,长度为35m,共计33根;格构柱GGZ2为610×610,角钢为等边角钢200×24,长度为40m,共计1根;格构柱GGZ3为460×460,角钢为等边角钢140×14,长度20m左右,共计3根。
常州地铁钻孔灌注桩施工照片

制表人:闫海 制表时间:2017年2月1日
1
提高钻孔灌注桩成孔质量
- 2 -

1
二、QC小组简介
五、设定目标
本QC小组于2017年2月成立,小组成员由10人组成,均已接受过QC学习培训。小组情况见表2
表2 小组成员情况一览表
小组名称
中铁十二局集团建筑安装工程有限公司常州地铁工程项目部QC小组
成立时间
2017年2月1日
注册时间
小组注