文档介绍:预应力混凝土管桩偏位的处理方法
摘要:随着预应力混凝土管桩的普遍应用,随之而来也产生了一些问题,本文通过工程实践表明在施工管桩时,虽然由于各种原因引起偏位,但桩身没有被破坏的,经过检测不影响继续使用的,可以根据各自的偏位程度,考虑采用推顶法或锚杆补桩法进行处理。
Abstract: With the widespread application of prestressed concrete pipe, there follows some problems too. According to project practice, in the process of pile construction, there are many causes will result in the deviation of the pile but the pile itself is un-damaged and will not be influenced to be used again through test. The deviation degree could be considered, the pile jacking method or bolt mend stakes method could be used to treat.
关键词:桩基施工;事故处理;推顶法;锚杆补桩法
Key words: pile foundation construction;accident management;pipe jacking;bolt mend stakes
中图分类号:TU81 文献标识码:A文章编号:1006-4311(2010)36-0072-01
1工程概况
笔者参加设计的淮阴发电有限公司1×300MW级上大压小热电联产二期工程烟囱底板基础,设计采用C80、
Φ600预应力高强度混凝土管桩86根,桩长20m, 桩截面进入持力层(粘土层)大于5m,采用10+10m焊接桩,单桩竖向承载力特征值1500 kN。打桩完成后,。烟囱底板基础范围内的土质分层(自上而下)情况为:①杂填土;①-2素填土,以淤泥质土、粉质粘土为主,混杂碎石、煤渣等;②粉质粘土,大多为可塑;③粉土,大多为可塑;④粉质粘土,可塑,土质不均匀;⑤粘土,硬塑,土质均匀,其中开挖范围内为①杂填土和①-2素填土。
该基础所在地原为池塘,基础底板位于素填土层内,。~。~,然后再采用人工挖掘的方法。机械挖土时采用一台单斗反铲挖土机,从东向西退挖,土方临时堆放在基坑南侧,,施工十分顺利。但在人工修挖基槽时,发现西南区域基坑内深黑色的杂填土将地表的素填土拱起,且次日部分桩有偏位现象出现。经对桩位的复核,发现偏移量在11~50cm的桩有18根,在51~80cm的桩有6根,以北区域内的桩基基本没有偏位。偏移量的分布有明显的规律,即从南向北递减,从东到西递增。
2管桩偏位原因及其解决思路
原因分析:该区域原为池塘边缘,南北侧的土质差异较大,北侧的粉质粘土层较好(γ=,c=13kPa,