文档介绍:STANDARD OPERATING PROCEDURES
SOP-MG-00 SITE MANAGEMENT
Ref. No. Contents
SOP-MG-01 Site Possession Process (Privates Project)
SOP-MG-02 anisation Chart
SOP-MG-03 Standard Operating Procedures
SOP-MG-04 Material Requisition
SOP-MG-05 Site Office ing Mail
SOP-MG-06 Site Office ing Mail
SOP-MG-07 Standard Filling System for Head / Site Office
PARK HYATT SAIGON HOTEL PROJECT
STANDARD OPERATION PROCEDURE NO
SOP –MG-01 ( Page 1/1 )
WORK TITLE :
Site possession Process ( Private Project )
APPROVED BY :
Head, Control Dept
CHECKED BY :
PROJECT MANAGER
REVISION : A
EFFECTIVE DATA :
WORKMANSHIP STANDARD : ACCEPTANCE /REJECTION CRITERIA
NA
REFERENCE STANDARDS/ CODES & QUALITY PLAN :
NA
FACILITIES /INSPECTION INSTRUMENT :
NA
ENVIRNMENT CONTROLS :
NA
NECESSARY RECORDS :
1. Letter from Architect specifying take over date
2. Site handing and taking over letter/form
FREQUENCY :
One time per project
SPECIAL REQUIREMENTS :
NA
SAFETY & HEALTH REQUIREMENTS
Safety Orientation Course for workers
WORK PROCEDURE
CHECKING METHOD
REMEDIAL MEASURE
RESPONIBILITY
Project Manager
Engineer
Foreman
Assistant Foreman
Trade Worker
Checker
Subcon
Contract Manager
1. Received letter from Architect specifying take over dated for possession
2..Arrange with Client/Consultant the exact date for visit and possession
3. Site visit and take instruction from Client/ Consultant
Management to highlight anything found not to be in order
all parties ate satisfied, signing of handing and taking over letter /form is carried out .site is then considered possessed
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
C
C
C
P
P
P
P
P
C
A
File : MG - 01 DISK: SOP A : APPROVE F : CONFIRM P : PERFORM C: CHECK
PARK HYATT SAIGON HOTEL PROJECT
STANDARD OPERATION PROCEDURE NO
SOP –MG-02 ( Page 1/2 )
WORK TITLE :
anization Chart
APPROVED BY :
Head, Control Dept
CHECKED BY :
PROJECT MANAGER
REVISION : A
EFFECTIVE DATA :