PARK HYATT SAIGON HOTEL PROJECT
STANDARD OPERATION PROCEDURE NO
SOP –ST – 06
WORK TITLE :
Lifting of precast follow core slab
APPROVED BY :
Head, Control Dept
CHECKED BY :
PROJECT MANAGER
REVISION : A
EFFECTIVE DATA : 18/5/98
WORKMANSHIP STANDARD : ACCEPTANCE /REJECTION CRITERIA
ply with specification
REFERENCE STANDARDS/ CODES & QUALITY PLAN :
ply with specialist requirement
FACILITIES /INSPECTION INSTRUMENT :
Hoist beam & clambers are attached with shackle/sling
ENVIRNMENT CONTROLS :
NA
NECESSARY RECORDS :
Shop drawings
FREQUENCY :
Every inspection
SPECIAL REQUIREMENTS :
NA
SAFETY & HEALTH REQUIREMENTS :
Check the safety working load for hoisting equipment
WORK PROCEDURE
CHECKING METHOD
REMEDIAL MEASURE
RESPOSIBILITY
Project Manager
Engineer
Foreman
Assistant Foreman
Trade Worker
Checker
Subcon
Others
delivery arrives inform the driver where to park the trailer
2. Slabs shall be off loaded using a lifting beam and clampers or a lifting beam and bells , Both syst