文档介绍:【副本】
华能呼伦贝尔能源开发有限公司
基本建设工程施工
牙克石热电厂负荷切换换热站及配套热网工程
(第二标段)
投标文件
包封A—技术文件材料
热力管网建筑、安装工程
项目名称: 热力管网建筑、安装工程
投标人: 黑龙江省六建建筑工程有限责任公司(盖章)
法定代表人
或其委托代理人: (签字或盖章)
日期: 2014 年 10月22 日
目录
第一节施工组织设计方案························································1
第二节工程概况································································2
第三节施工主要措施·····························································3
第四节施工的技术管理···························································5
第五节工程管理································································6
第六节各分部分项工程主要施工方法···············································6
第七节关键部位施工方法·······················································12
第八节季节性施工措施··························································13
第九节施工组织机构及劳动力计划···············································14
第十节换热站工程······························································15
第十一节文明施工措施··························································19
第十二节安全保证的措施·······················································19
第十三节冬雨季施工措施·······················································21
第十四节工程质量保证措施······················································23
第十五节工期保证措施··························································26
附件1 用于本工程项目的主要施工机械装备一览表··································29
附件2 用于本工程项目的主要施工检验仪器一览表··································30
附件3 本工程项目劳动力计划表··················································31
附件4 临时用地表······························································31
附件5 组织机构框架图··························································32
附件6 管理人员相关证件·······················································33
附件5 安全技术交底
牙克石地区供热综合改造工程
第二标段施工组织设计方案
批准:

审核:
编制:
江苏盛业建设集团有限公司
2015年7月

工程施工组织设计
工程概况
本工程为牙克石热电厂负荷切换换热站及配套热网工程,管道管径为DN500-DN100,管线总长度为3773X2米。
一级网:将新建换热站与原有高温管网连接,即从奋斗街与建设路之交叉口处原有DN800管线上接出DN400管线,沿建设路向南敷设至新建换热站;另一路由牙克石热电厂3×14MW热水锅炉房热源出口管径为DN450的管线上接出DN400管线,沿锅炉房围墙向西敷设至换热站。
二级网:
1、首先将原有北方药业热电厂低温水网分断,利用作为换热后的二级网,