文档介绍:STANDARD OPERATING PROCEDURES
SOP-CE-00 CIVILING ENGINEERING
. Contents
SOP-CE-01 Excavation and Filling of Embankment
SOP-CE-02 Underground Drainage System
SOP-CE-03 Construction of Retaining Wall
SOP-CE-04 Construction of CE drain (Stormwater Drain)
SOP-CE-05 Construction of Interlocking Paving Block Driveway
SOP-CE-06 Construction of Sewers
SOP-CE-07 Construction of Premix Bituminous Driveway
SOP-CE-08 Turf Planting
SOP-CE-09 Tree / Palm Planting
SOP-CE-10 Construction of Grass Cell Paver for Hardstanding
SOP-CE-11 Laying of Sub Soil Pipes
SOP-CE-12 General Refilling of Trenches
PARK HYATT SAIGON HOTEL PROJECT
STANDARD OPERATION PROCEDURE NO
SOP – CE - 01 ( Page 1 / 2 )
WORK TITLE :
Excavation and filling of embankment
APPROVED BY :
Head, Control Dept
CHECKED BY :
PROJECT MANAGER
REVISION : A
EFFECTIVE DATA : 1-12-98
WORKMANSHIP STANDARD : ACCEPTANCE /REJECTION CRITERIA
ply with the specification
REFERENCE STANDARDS/ CODES & QUALITY PLAN :
ply with BOWEC ‘s requirement and spec
FACILITIES /INSPECTION INSTRUMENT :
Theodolite , dumpy level, cable detector
ENVIRNMENT CONTROLS :
ply with MOE’s requirement
NECESSARY RECORD
Surveyor setting out drawing , services drawing
FREQUENCY
Every inspection
SPECIAL REQUIREMENTS :
NA
SAFETY & HEALTH REQUIREMENTS :
area of excavation
mosquito breeding
WORK PROCEDURE
CHECKING METHOD
REMEDIAL MEASURE
RESPOSIBILITY
Project Manager
Engineer
Foreman
Assistant Foreman
Trade Worker
Checker
Subcon
Surveyor
to pegs out and transfer the points/lines from bench marks
out pegs to be protected with cement mortar or barricade
all the underground service
water is left to stagnate, construct temporary drain for water discharge
trap, wash bay and temporary drain must be constructed before removing soil off site
Cross check the lines
Visual inspection
licensed cable detec